Specifications
SECURITY CAMERA SYSTEM UPGRADE AND REPLACEMENT
FOR MONTGOMERY COUNTY DETENTION CENTER
GENERAL CONDITIONS GC-36
9.5.5 Payment to material suppliers shall be treated in a manner similar to that provided in
Subparagraphs 9.5.2, 9.5.3 and 9.5.4.
9.5.6 A Certificate for Payment, a progress payment, a recommendation for a Certificate for
Payment or partial or entire use or occupancy of the Project by the Board shall neither constitute
acceptance of Work not in accordance with the Contract Documents nor act as a waiver of any
claim.
9.5.7 Subject to the provisions of the Contract Documents and the Ohio Revised Code, the amount
of each progress payment shall be computed as follows:
9.5.7.1 take that portion of the Contract Sum properly allocable to completed Work
as determined by multiplying the percentage completion of each portion of
the Work by the share of the total Contract Sum allocated to that portion of
the Work in the schedule of values and Wage Determination, less retainage
as provided by Ohio Revised Code Sections 153.12, 153.13, 153.14 and
153.63, as may be amended. Pending final determination of cost to the
Board of changes in the Work, amounts not in dispute may be included as
provide in Subparagraph 7.3.7 even though the Contract Sum has not yet
been adjusted by Change Order and Board Resolution;
9.5.7.2 add that potion of the Contract Sum properly and legally allocable to
materials and equipment delivered and suitably stored at the site for
subsequent incorporation in the completed construction (or, if approved in
advance by the Board, suitably stored off the site at a location agreed upon
in writing), less retainage as provided by Ohio Revised Code Sections
153.12, 153.13, 153.14 and 153.63 as may be amended;
9.5.7.3 subtract the aggregate of previous payments made by the Board; and
9.5.7.4 subtract amounts, if any, for which the Engineer or Board has withheld or
nullified a Certificate of Payment or a recommendation for same as provided
in Paragraph 9.4.
9.5.8 The progress payment amount determined in accordance with Subparagraph 9.5.7 shall be
further modified under the following circumstances:
9.5.8.1 subtract, upon Substantial completion of the Work, a sum as determined by
the Engineer and the Board for incomplete Work and unsettled claims; and
9.5.8.2 add, if final completion of the Work is thereafter materially delayed through
no fault of the Contractor, any additional amounts payable in accordance
with Subparagraph 9.9.3.
9.5.9 Progress payments shall have no relationship to the transfer of title in the Work absent an
express written agreement to the contrary signed by both the Board and Contractor and specifically










