Specifications
SECURITY CAMERA SYSTEM UPGRADE AND REPLACEMENT
FOR MONTGOMERY COUNTY DETENTION CENTER
GENERAL CONDITIONS GC-32
Time and if the performance of the Work is not, was not or would not have been delayed by any
other cause for which the Contractor is not entitled to an extension in the Contract Time under the
Contract Documents. The Contractor further acknowledges and agrees that adjustments in the
Contract Time will be permitted for a delay only to the extent such delay (1) is not caused, or could
not have been anticipated, by the Contractor, (2) could not be limited or avoided by the Contractor's
timely notice to the Board of the delay and (3) is of a duration of not less than one (1) day. In the
event the Engineer and Board cannot agree upon a reasonable time, the decision of the Board shall
control.
8.3.2 Claims relating to time shall be made in accordance with applicable provisions of Paragraph
4.2.
8.3.3 Notwithstanding anything to the contrary in the Contract Documents, extensions of the
Contract Time, to the extent permitted under Paragraph 8.3.1, shall be the sole remedy of the
Contractor for any (1) delay in the commencement, prosecution or completion of the Work, (2)
hindrance or obstruction in the performance of the Work, (3) loss of productivity, or (4) similar
claims (collectively referred to in this Paragraph 8.3.3 as Delays) whether or not such Delays are
foreseeable. In no event shall the Contractor be entitled to any compensation or recovery of any
damage, in connection with any Delay, including, without limitation, consequential damages, lost
opportunity costs, interest or similar claims.
ARTICLE 9 - PAYMENTS AND COMPLETION
9.1 Schedule of Values
9.1.1 Schedule of Values. Within ten (10) days after execution of the Agreement, the Contractor
shall submit to the Engineer a schedule of values allocated to various portions of the Work, prepared
in such form and supported by such data to substantiate its accuracy as the Engineer or Board may
require. This schedule, unless objected to by the Engineer, shall be used as a basis for reviewing
the Contractor's Applications for Payment.
9.1.2 Material Sources and Substitutions. Within ten (10) days after execution of the Agreement,
the Contractor shall furnish the Board with a list of materials and suppliers upon which the
Contractor's bid was based. Whenever a substitution of materials is proposed on an "approved
equal" basis, Contractor shall submit such substitutions for approval by the Board.
9.2 Applications for Payment
9.2.1 At least ten (10) days before the last day of each calendar month, unless otherwise required
by the Contract Documents, the Contractor shall submit to the Board an itemized Application for
Payment for operations completed in accordance with the schedule of values. Such application shall
be notarized and supported by such data substantiating the Contractor's right to payment as the
Board or Engineer may require, such as, but not limited to, copies of requisitions from
Subcontractors and material suppliers, and reflecting retainage if provided for elsewhere in the
Contract Documents or as required by law. A copy of the Application for Payment shall be
submitted to the Engineer contemporaneously with submission of the original Application for
Payment to the Board.