SECURITY CAMERA SYSTEM UPGRADE AND REPLACEMENT
FOR MONTGOMERY COUNTY DETENTION CENTER
SECURITY CAMERA SYSTEM 17000-23
B. Work Included:
1. Furnish all materials and labor necessary to complete the installation of
specific systems described herein and as shown on the plans and an
integration of all systems as indicated, specified herein or both. The work
of this Section includes, but is not necessarily limited to, the following:
a. Power Supplies, Cables and Conductors
b. Door Control System
c. Closed Circuit Television System
d. Intercom System
e. Paging System
f. Control Panels/Control Consoles
g. Security Monitoring and Control System
h. System Integration of all Systems
C. Reference Specifications, Materials, and/or Codes:
1. NEC 2008
D. Manufacturer’s Recommendations:
1. All systems described herein shall be fabricated and installed in strict
accordance with the manufacturer's published recommendations and in
compliance with all applicable building codes and regulations.
E. Cooperation with other Trades:
1. The Contractor shall coordinate the work of this Section with that of the
Division 16 contractor to ensure that the entire work of this project will
be carried out in an orderly, complete and coordinated fashion.
F. Submittals:
1. Substitutions: Contractors, subcontractors, suppliers and manufacturers
may request the approval of the Engineer to substitute materials, products
or equipment for the specified products, unless noted otherwise. The
Engineers approval will be required even though "or equal" or
synonymous terms are used. It shall be the responsibility of the
Contractor to assume all costs incurred because of additional work and/or
changes required to incorporate the proposed substitute into the project,
including possible extra compensation due to the Engineer.