Specifications
SECURITY CAMERA SYSTEM UPGRADE AND REPLACEMENT
FOR MONTGOMERY COUNTY DETENTION CENTER
SECURITY CAMERA SYSTEM 17000-7
e. Their field assembly and internal connection as may be necessary
for their proper operation.
f. Their mounting in place including the purchase and installation of
all supporting members, and fastening necessary to adapt them to
architectural and structural conditions.
g. Their connection to building systems including the purchase and
installation of all terminating fittings necessary to adapt and
connect them to the building systems.
2. Where applicable, items which are to be installed but not purchased as
part of the work of Division 17 shall be carefully examined upon delivery
to the project. Claims that any of these items have been received in such
condition that their installation will require procedures beyond the
reasonable scope of the work will be considered only if presented in
writing within one week of the date of delivery to the project of the items
in question. The work under Division 17 shall include all procedures,
regardless of how extensive, necessary to put into satisfactory operation,
all items for which no claims have been submitted as outlined above.
3. The specifications for the overall construction of the project, under the
general construction contract, delineate various items of work under
separate section headings. As described in the following paragraphs this
delineation is defined to the extent that it affects the Division 17 work
category. In the absence of more detailed information, these tasks shall
be taken as a specific instruction to Division 17 Contractors to include the
work assigned to them. Indications that each Contractor is to perform an
item of work means that he is to perform the work for his own
accommodation only, unless specifically noted otherwise.
4. Division 17/Division 16/ delineation of work shall be as follows:
a. Division 17 Contractor shall be responsible for furnishing and
installing all equipment, wiring, installation and testing of systems
defined in Division 17.
b. All wiring to final connections for CCTV system and new
Wonderware HMI monitoring systems shall be the responsibility
of Division 17.
c. Division 16 Contractor shall be responsible for ensuring that
emergency power is provided to all security systems.
d. Division 16 Contractor shall be responsible for ensuring that all
security systems equipment is powered from an uninterruptible
power system (UPS). Division 16 shall be responsible for
distributing UPS power to the security equipment.