Specifications

5. Operational Testing: The contractor shall perform thorough operational testing and
verify that all system com ponents are fully operational.
6. Hard-copy System Printout: The contractor shall subm it a hard-copy system printout
of all com ponents tested and certify 100 percent operation indicating all
devices/panels/units have passed the test criteria set forth by the m anufacturer.
7. Acceptance Test Plan Form: An acceptance test plan form shall be prepared/
provided by the contractor prior to the acceptance walk-through.
8. This form shall include separate sections for each device/panel/unit as well as a
colum n indicating the manufacturer's performance allowance/m argin, a column
indicating the result of the testing perform ed by the contractor (pass/fail), and an
warrantee colum n for recording The m anufacturers warrantee one the particular
piece of equipm ent.
9. Fire Alarm System s shall com ply with NFPA 72 Standards for inspection, testing, and
maintenance.
J. The contractor shall certify com pletion in writing and schedule the com m issioning
walk-through. The contractor shall provide all the tools and personnel needed to conduct an
efficient com m issioning process.
3.2 FIELD QUALITY CONTROL
A. Installation contractor shall subm it a written test report that the system has been 100
percent tested and approved. Final test shall be witnessed by the owner, engineer, electrical
contractor, chief security officer, and perform ed by the installation contractor. Final test
report shall be received and acknowledged by the owner prior to request for final paym ent.
B. Provide instruction to the owner's satisfaction with regard to proper use and operation of the
system .
C. Determ ine and report all problems to the m anufacturer's custom er service departm ent.
3.3 ADJUSTING
A. System maintenance and repair of system or workmanship defects during the warranty
period shall be provided by the Contractor free of charge (parts and labor).
B. Periodic testing of the system shall be carried out on a monthly or quarterly basis to ensure
the integrity of the control panel, the sensing devices, and the telephone lines.
C. The installer shall correct any system defect within six hours of receipt of call from the
Owner.
3.4 DEMONSTRATION
A. Demonstrate at final inspection that surveillance system and devices functions properly.
1. The Contractor upon com pletion of installation shall furnish training in the com plete
operation of the systems. A m inim um of 4 hours shall be provided for this training.
3.5 PROTECTION
A. Protect installed products until com pletion of project.
B. Touch-up, repair or replace dam aged products before substantial com pletion.
3.6 A. SECURITY DEVISES TO BE FURNISHED:
Bosch D9412GV4 control panel
Bosch D7412GV4 control panel
D1260 Keypads, Black
D9210C Access Module, each panel
B308 SDI2 bus relay module
B208 SDI2 bus input m odules as needed
D9127T Popit m odule as needed
D8125 Popex zone expander, as needed for one in each panel
D101 Lock and Key
D110 Tam per switches
D8103 Enclosure as needed
D9131A Printer module
Blue Line Series Motion Detectors, Tri-Tech only as needed
EK-150RT out door sirens,. Stainless Steel
D56 Com m and Center Box as needed
DS1102i Glass break detectors
ISN-CMET-200AR Door Contact
INS-CMET-4481 Overhead garage door contacts
12vdc, 7amp batteries
Page 14