6.0 INSTALLATION - ELECTRICAL REQUIREMENTS
ALL  WIRING  MUST  BE CARRIED  OUT  IN  ACCORDANCE  WITH  CURRENT  IEE  WIRING 
REGULATIONS.
The AMPTEC  boiler  must  be  installed  by  a  qualied  competent  tradesman  in  accordance  with  supplied 
instructions and drawings to ensure correct operation. 
Check the main incoming supply to the property to ensure there is sufcient current and voltage for the size 
of the boiler or boilers to be installed.  Remember to also take account of the supply requirements for the rest 
of the property. Ensure the correct cable size is used to feed the boiler (refer to IEE wiring regulations).
A double pole RCD with a trip level sensitivity of 30mA and capable of breaking the full load current to BS 
EN 61008:1994, must be used.
In order to provide a means of isolation, the boiler must be connected to the supply through a double pole 
linked switch with a minimum contact gap of 3mm in all poles. The RCD is suitable for this requirement if it 
is mounted in close proximity to the boiler.
A correctly rated MCB must be used in the supply, see Technical Specications. An additional 3A supply is 
required for the controls etc. NOTE, a blank must be tted between each MCB to provide ventilation, check 
with the MCB manufacture/supplier.
NOTE: The high current mains supply MUST NOT be routed through the programmer, controls etc. Follow 
the wiring diagrams.  Use a standard programmer,  room  thermostat,  etc.     The high current switching is 
carried out inside the boiler, only standard switched live (low current) control signals are supplied by the 
programmer etc.
Electrical Connections
Access can be gained to the electrical connections by removing the top front panel.
1  CONN5:  MAIN POWER.Main power-supply cables.  Connect the power cables from the power “supply”  
(CONN5) terminals on the PCB assembly in the boiler directly to the isolation switch, live, neutral and 
earth. Use the correct rated cable. Do not connect the power through the programmer, thermostats 
etc.  The main power PCB terminals in the boiler are suitable for cables up to 10mm
2
.  NOTE:  THESE 
CONNECTIONS MUST BE TIGHT.  LOOSE CONNECTIONS WILL CAUSE A FIRE.  BURNING AT 
CONN5 CONNECTOR IS NOT COVERED BY THE WARRANTY.
2  CONN1, pins 2 & 3:  CONTROL SIGNAL.Connect switched live to ‘R’ and neutral to ‘N’ on the control 
terminal block in the boiler to the switched live and neutral from the programmer control   
circuit. A neutral must be connected, as this control signal is optically isolated from the main supply 
in the boiler and will not run without a neutral. Do not connect any wires to the terminal marked N/C.
3  CONN1  pins  4,  5  &6:PUMP  CONNECTIONS.The  supply  to  the  pump  must  be  connected  to  the  
‘PUMP’ terminal on the control terminal block in the boiler. This supply is fused in the boiler at 2A.               
 4. Cable access is made from either the right or left hand side via the X3 knockouts provided 
 (x1 25mm for power and x2 20mm for pump and thermostat cables). Having decided which side to 
 route the cabes, remove x3 knockouts only (This can be achieved with a small tap from a ball 
 nosed hammer, then twisting the knockout untill it is removed. Note: Take care not to damage the 
 casing, ensure the metal discs are retreived and no sharp edges are present. The cables should be      
 installed using a suitable strain relief bush (not supplied).
X3 KNOCKOUTS
LEFT HAND SIDE
X3 KNOCKOUTS 
RIGHT HAND SIDE
FIGURE FIVE: