User's Manual
Table Of Contents
- Altiostar Networks iRM4451nn00-2 intelligent Remote Radio Head
- Preface
- Contents
- List of tables
- List of figures
- 1 Introduction
- 2 Safety requirements
- 3 Physical description
- 4 Installation prerequisites
- 5 Installation overview
- 6 Installing the iRM4451nn00-2
- 6.1 Assembling cables
- 6.2 Routing pre-assembled power/GigE optical fronthaul/grounding cables
- 6.3 Installing the mounting bracket
- 6.4 Hoisting the iRM4451nn00-2 on elevated structures
- 6.5 Installing the iRM4451nn00-2 on the mounting bracket
- 6.6 Connecting the grounding cable
- 6.7 Connecting the RET cables
- 6.8 Connecting the GigE optical fronthaul cables
- 6.9 Connecting the RF cables
- 6.10 Connecting the alarms cable
- 6.11 Connecting the –48 V dc power cable
- 6.12 Weatherproofing cable connections
- 6.13 Checking power
- 7 Terms, Acronyms and Abbreviations
Installing the iRM4451nn00-2
6-4 iRM4451nn00-2 iRRH Product Description and Installation Guide
6.3 Installing the mounting bracket
The iRM4451nn00-2 is shipped from the factory with the mounting plate pre-installed
on the chassis as shown in Figure 6-3.
Figure 6-3 iRM4451nn00-2 mounting plate
6.3.1 Mounting on a pole/mast
The following procedure provided instructions for mounting the iRM4451nn00-2 on a
pole/mast using the supplied mounting bracket assembly.
To install mounting plate on a pole or mast:
1. Install the mounting bracket and mounting clamp onto the pole/mast with
mounting hardware as shown in
Figure 6-4.