User's Manual

Table Of Contents
Installation overview
iRM4451nn00-2 iRRH Product Description and Installation Guide 5-1
5 Installation overview
This section provides an overview of the installation procedures and instructions for
installing the Altiostar Networks iRM4451nn00-2 intelligent Remote Radio Head.
All required cabling for grounding, power, fronthaul, RF and optional GPS, are supplied
by the Installer, as provided in the Site Installation Plan, and should already be pre-
installed with drops to the iRRH location, or according to local practice.
5.1 Installation procedures
The following list describes the top-level iRM4451nn00-2 installation procedures. You can
instantly navigate to any procedure by clicking on the procedure with the mouse.
Unpacking the shipping container on page 5-1
Verifying all parts received on page 5-2
Assembling cables on page 6-1
Verify Installer-supplied –48 V dc power cable on page 6-1
Verify Installer-supplied GigE optical cable on page 6-1
Verify Installer-supplied grounding cable on page 6-1
Routing pre-assembled power/GigE optical fronthaul/grounding cables on
page 6-2
Mounting on a pole/mast on page 6-4
Mounting on a wall on page 6-5
Hoisting the iRM4451nn00-2 on elevated structures on page 6-6
Installing the iRM4451nn00-2 on the mounting bracket on page 6-7
Connecting the grounding cable on page 6-8
Connecting the RET cables on page 6-9
Connecting the GigE optical fronthaul cables on page 6-10
Connecting the RF cables on page 6-10
Connecting the alarms cable on page 6-11
Connecting the –48 V dc power cable on page 6-11
Weatherproofing cable connections on page 6-11
Checking power on page 6-12
5.2 Unpacking the shipping container
The following procedure describes removing the iRRH from the shipping container,
inspecting the contents for damage, and what to do if damage is found.