iRM4451nn00-2 iRRH Product Description and Installation Guide 4-5
Table 4-3 Site pre-installation visit checklist
Item
Site pre-installation visit checklist Check
1
Verify Site Installation Plan and installation documentation is available.
2
Verify health and safety documentation specified by the Operator and Altiostar Networks
are understood and installation personnel are trained accordingly.
3
Know locations of fire equipment, eyewash stations, and evacuation procedures posted
for fire/halon discharge.
4
Know locations of first aid and emergency equipment and installation personnel are
familiar with their operation and use.
5
Verify site authorizations, clearances, and releases from Operator and local authorities
are complete.
6
Verify emergency telephone numbers are posted for fire, police, and ambulance/medical
aid.
7
Verify contact information for the Operator or his representative(s), the Installer, and
local authorities are posted.
8
Verify installation schedule is approved.
9
Wear approved protective equipment such as hard hats, safety glasses, gloves, etc.
when needed.
10
Verify the installation location of the iRRH meets the mounting requirements indicated in
this document.
11
Verify main power supply is properly installed and tested and capable of supplying the
required voltage (–55.2 £ –48.0 £ –43.2 V DC) and current for proper operation of the
iRRH.
12
Verify –48 V DC power cable to the iRRH is labeled and tested as specified in the Site
Installation Plan.
13
Verify recommended size breakers/fuses for the external power source is properly
installed and capable of protecting the –48 V DC power to the unit.
14
Verify earth ground bonding point, for connection of the grounding cable to the iRRH is
correctly installed, labeled and tested as specified in the Site Installation Plan.
15
Determine a safe method to hoist and secure iRRH into position on selected structure
and enter into Site Installation Plan.
16
Verify proper in-line surge protectors are installed, where required, on power and RET
cables as specified in the Site Installation Plan.
17
Verify that the Operator, Installer, Altiostar Networks and all other affected parties are in
agreement with the equipment installation location, power source, and grounding
location, to meet the installation checklist requirements.