Installation Guide
Table Of Contents
- Preface
- Contents
- 1 Introduction
- 2 Safety requirements
- 3 Physical description
- 4 Installation prerequisites
- 6 Installing the iRM4451
- 6.1 Assembling cables
- 6.2 Routing pre-assembled power/GigE optical fronthaul/grounding cables
- 6.3 Installing the iRM4451 mounting bracket
- 6.4 Hoisting the iRM4451 on elevated structures
- 6.5 Installing the iRM4451 on the mounting bracket
- 6.6 Connecting the grounding cable
- 6.1 Connecting the RET cables
- 6.1 Connecting the GigE optical fronthaul cables
- 6.1 Connecting the –48 V dc power cable
- 6.2 Checking power
- 6.3 Installing the solar shield
- 7 Terms, Acronyms and Abbreviations
- 5 iRM4451 installation overview
Installing the iRM4451
iRM4451 RRH Product Description and Installation Guide 6-7
NOTE
Because of the differences Operator is responsible for determining an
industry-approved, safe method of hoisting the iRM4451 into position
onto elevated structures.
WARNING
Be sure to follow all established Operator local practice and safety
precautions when hoisting the equipment on elevated structures.
Figure 6-16 Hoist line carabiner attachment point
6.5 Installing the iRM4451 on the mounting bracket
This section provides the procedure for installing the iRM4451 main unit on the
installed mounting bracket.