Installation Guide
Table Of Contents
- Preface
- Contents
- 1 Introduction
- 2 Safety requirements
- 3 Physical description
- 4 Installation prerequisites
- 6 Installing the iRM4451
- 6.1 Assembling cables
- 6.2 Routing pre-assembled power/GigE optical fronthaul/grounding cables
- 6.3 Installing the iRM4451 mounting bracket
- 6.4 Hoisting the iRM4451 on elevated structures
- 6.5 Installing the iRM4451 on the mounting bracket
- 6.6 Connecting the grounding cable
- 6.1 Connecting the RET cables
- 6.1 Connecting the GigE optical fronthaul cables
- 6.1 Connecting the –48 V dc power cable
- 6.2 Checking power
- 6.3 Installing the solar shield
- 7 Terms, Acronyms and Abbreviations
- 5 iRM4451 installation overview
Installation prerequisites
iRM4451 RRH Product Description and Installation Guide 4-1
4 Installation prerequisites
This section contains information on the documentation, tools, equipment, and
conditions required for performing the installation procedure. The document assumes
that the target audience has reasonable industry experience, is qualified, and has
installed wireless base stations in the past.
4.1 Required tools
A typical telecommunications technician's toolkit is required to complete the iRM4451
installation. Additional required specialty tools and consumables are listed in
Table 4-6.
Table 4-6 Required tools
Required Tools
ESD wrist grounding
strap
Torque screwdriver and
assorted bits
Box cutter Digital voltmeter
Torque wrench, open-
end, 8
mm
Crimp tool (2 to 8 AWG)
Cordless electric
screwdriver
Cable tie tool