User's Manual

Installation prerequisites
3-4 iRU4438 iRRH Product Descripton and Installation Guide
3.5 Site installation checklist
Verify site conditions required for the installation of iRRH are known. In addition, the
site must be prepared by the Operator in accordance with the Site Installation Guide
provided by the Operator which must include, at a minimum, the required tasks in
Table .
13
Verify recommended size breakers/fuses for the external power source is properly
installed and capable of protecting the 110/220 V ac power to the unit.
14
Verify earth ground bonding point, for connection of the grounding cable to the
iRU4438 iRRH, is correctly installed, labeled and tested as specified in the Site
Installation Plan.
15
Determine safe method to hoist and secure iiRU4438 RRH into position on selected
structure and enter into Site Installation Plan.
16
Verify proper in-line surge protectors are installed, where required, on power/RF/
fronthaul/backhaul cables to iRU4438 iRRH as specified in the Site Installation Plan.
17
Verify that the Operator, Altiostar Networks and all other affected parties are in
agreement with the equipment installation location, power source, and grounding
location, to meet the installation checklist requirements.
Item
Site pre-installation visit checklist Check
Table 3-3 Site installation checklist
Item Site installation checklist Check
1
Verify Site Installation Plan and installation documentation is available.
2
Verify health and safety documentation specified by the Operator and Altiostar
Networks are understood and installation personnel are trained accordingly.
3
Know locations of fire equipment, eyewash stations, and evacuation procedures posted
for fire/halon discharge.
4
Know locations of first aid and emergency equipment and installation personnel are
familiar with their operation and use.
5
Verify site authorizations, clearances, and releases from Operator and local authorities
are complete.
6
Verify emergency telephone numbers are posted for fire, police, and ambulance/
medical aid.
7
Verify Operator and local authorities contact and phone numbers are posted.
8
Verify installation schedule is approved.
9
Wear approved protective equipment such as hard hats, safety glasses, gloves, etc.
when needed.
10
Verify pre-installation work specified in the Site Installation Plan is complete.
11
Verify the installation location of the iRRH meets the mounting requirements indicated
in this document.