2. Turn-Up and Test
31 031-132-B0-001 Rev. A
TM
©2000
2.2 Initial Operation, continued
2.2.3 Starting a Local APU Test, continued
11. Adjust pre-regulator, or dual regulator (located on gas bottle assembly
for Propane) if necessary by removing regulator cap and adjusting for
11 ±1 of water column pressure.
12. Set RAS to STOP.
13. Remove brass manometer fitting and re-install plug to demand
regulator input monitoring port using approved pipe sealant.
14. Check demand regulator input monitoring port for leaks.
15. Set RAS to AUTO.
16. To continue functional test on power node system, refer to ECM
certification section in ECM manual (744-862-C0) page 47.