completion report and request for factory commissioning
During commissioning, the heat pump system will be inspected to ensure that it is functioning properly. This ensures
that all factory specifications have been checked and that the system can operate reliably over an extended period.
The factory commissioning involves costs and is mandatory for extension of the warranty services.
□
Initial commissioning
□
Repeat commissioning
Heat pump type Regulator type
contractor end customer / operator
□
Electric
□
Heating
□
other company
Company
Contact Name / First name
Street address Street address
ZIP code / head office ZIP code / city
Phone Phone
Preferred date Alternate date
Date / time Date / time
The completion report should be submitted 8 work days before the desired commissioning date. If there is a conflict with the date,
you will be contacted by phone.
I/we hereby confirm that all preliminary work required for commissioning has been carried out and completed. The system is
ready for operation.
The attached general checklist is provided for information purposes; all items should be checked.
Has the heating system been filled and depressurised; do the circulation pumps function
properly?
□
No
□
Yes
Is the heat source system completed, inspected and OK?
□
No
□
Yes
Have the heating circuit, heat source system and circulating pumps been bled?
□
No
□
Yes
Are all electrical components permanently connected according to the circuit diagram, are all
sensors mounted correctly?
□
No
□
Yes
Have all volume flows and water flow rates been checked and are they OK?
□
No
□
Yes
In the event that the heat pump system is not ready for operation and if installation work has to be performed by the commissioning
technician during commissioning, this will involve charges to the contractor. If the heat pump system is not ready for operation, the
commissioning technician can request a repeat commissioning, which will involve additional costs.
The contractor or an authorized representative must be present during commissioning.
The operator of the system should be present during commissioning in order to ensure that proper instruction
is received.
An acceptance report will be prepared during commissioning.
I, the undersigned, hereby request commissioning, in return for a fee.
Invoice to
□
Contractor
□
End customer / operator
Place, date Name (block letters) Signature / company stamp
FAZ-WP Formblatt UK820522c Stand: 240407
Completion report for heat pump systems