Specifications

25
We reserve the right to modify technical specifications without prior notice.
UK830301/170306 © Alpha-InnoTec GmbH
Overflow valve
Set the overflow valve so that the spread between the for-
ward and return ow is 10K (set at the factory to 200 mbar
and sealed by paint).
Insulating the hydraulic
connections
NOTICE.
Insulate the heating circuit and the heat
source according to local applicable stan-
dards and directives.
The angle ball valves of the connections on the module box
must be opened.
Check seals of all hydraulic connections. Conduct
pressure test.
Remove insulation material for internal piles from
the extra box.
Insulate all connections, angle ball valves, vibra-
tion decouplers, connections and lines of the heat
source in the unit so that they are vapor diffu-
sion-tight...
For units with cooling function, insulate angle ball
valve and connecting pipe so that they are vapor
diffusion-tight...