Specifications
10
We reserve the right to modify technical specifications without prior notice.
83050800aUK – Translation of the operating manual  © Alpha-InnoTec GmbH
 NOTE.
  Always refer to and follow the installation plan 
for the respective model. Note the size and 
minimum clearances.
  Installation plan for the respective model.
 IMPORTANT
  The heat pump must be installed on a rm, 
horizontal oor. Ensure that the oor is designed 
for the weight of the heat pump.
  Do not use a rigid foam boiler pedestal
 “Technical data/Scope of delivery” overview, 
“General unit data” section.
 NOTE.
  Install the unit so that the operator side is 
accessible at all times!
 IMPORTANT
  Do not tilt the unit more than a maximum of 45° 
in any direction.
 NOTE.
  The openings for the pallet truck must be closed 
off using the cover plates supplied!
Detailed drawing of concrete foundation: 
1 Screed
2  approx. 100 mm
3  Structural borne sound insulation 
depending on weight of heat pump
4  Concrete foundation
5  Perimeter insulation strips
6  Impact sound insulation
7  Concrete ceiling
 IMPORTANT
  Do not tilt the unit more than a maximum of 45° 
in any direction.
To prevent transport damage, you should transport the 
unit to its nal place of installation in its packed condition 
(on the wooden pallet with packaging) using a pallet 
truck.
  Remove packaging and set extra box aside (will be 
needed later on!)...
  Move the pallet truck under the unit…
 NOTE.
  The two openings for the pallet truck must be 
closed off using the cover plates supplied (two 
screws each).
 NOTE.
  Please always close off the transport openings to 
reduce noise!
installation
CAUTION!
  Several people are required to install the 
unit.
 NOTE.
  Take into account the size of the unit.
 “Technical data / Scope of delivery” overview, 
“General unit data” section.