3 OPERATION
3.1 Emergency
There are three major steps, Deployment, Active and Mounting, which has to be followed
as below in emergency situation.
3.1.1 Deployment Process
Figure 3-1-1 Deployment process
Step 1:
Lift Carry Bag out of
bracket on the wall.
Step 2:
Bring Carry Bag and jump
into a Life Boat.
Step 3:
Open Carry Bag and take
AIS SART, Extension Pole
and buoyant lanyard out
Step 4:
Connect and rotate
extension pole into
PLOMO-500.
Step 5:
Remove the bottom cover
and extend pole up to 1
Meter