Chapter 6 Safety Application Development
Commissioning Life Cycle
The flowchart below shows the steps required for commissioning a
GuardLogix system. The items in bold text are explained in the
following sections.
Commission the System
Specify the Control Function
Create Project
Online
Create Project
Offline
Attach to Controller and Download
Test the Application
Program
Generate Safety Task Signature
Confirm the Project
Record Safety Task
Signature
Project Verification Test
Safety Validation (Independent Review)
Lock the Controller / End
Make required
modifications
Delete Safety Task
Signature
Tests
Passed?
Project
Valid?
No
Yes
No
Yes
Fill out the Safety Checklists in Appendix
D