5 PROCEDURE AND SETTINGS UP TO THE POINT OF OPERATION
5
5 PROCEDURE AND SETTINGS UP TO THE POINT OF OPERATION
This section explains the operating procedure up to the point the CC-Link board is
operated, as well as the names and setting for each part of the CC-Link board, wiring
method and hardware testing.
5.1 Procedure Up to the Point of Operation
An outline of the procedure up to the point of CC-Link board operation is explained
below.
Start
Perform
CC-Link
board settings.
Do the wiring between the
CC-Link board and the master module.
Turn on the power to the PC and install the software package.
Test the
CC-Link
board.
Perform data link settings for the
CC-Link
board.
Startup the CC-Link system.
Execute PC programs.
Complete
See Section 5.3, "Name and Setting for Each Part."
See Section 5.4,
"Connecting Modules Using the CC-Link Dedicated Cable"
See Chapter 6,
"INSTALLING AND UNINSTALLING SOFTWARE PACKAGE."
See Section 7.2.8,
"Operation of the Memory I/O Test screen"
See Section 7.2,
"CC-Link Utility"
· · · · · ·
· · · · · ·
· · · · · ·
· · · · · ·
· · · · · ·
If the power to the PC is on, turn the power off.
Remove the
CC-Link board
terminal block.
Install the
CC-Link board
into the PC.
Fix the
CC-Link board
with the PC's board fixing screws.
Install the
CC-Link board
terminal block.
Note
Setting on the master module side is mandatory in order to run the CC-Link system.
Perform the settings for the master module side as required.
See the user manual for the master module regarding the master module settings.