10 Click Next in each subsequent panel until the “Database Alignment” panel is
displayed.
11 Configure the “Enable Database Alignment” parameter.
12 If you selected the “Enable Database Alignment” parameter in step 11, select a
server to act as the preferred server.
13 Click Next.
14 Click Next in each subsequent panel until the “Installation Complete” panel is
displayed.
15 Select the “Start the 5620 SAM Main Server” parameter.
16 Click Done to close the server configuration utility.
17 Enter the following to switch back to the samadmin user:
# exit
18 Verify the standby main server has started.
19 Log out of the standby main server.
20 Perform steps 1 to 19 on the primary main server.
21 If required, perform Procedure 8-3 to perform a server activity switch and revert
the main servers to their original roles.
Procedure 8-8 To reinstantiate a redundant database using the
5620 SAM client GUI
Perform this procedure to re-establish redundancy after a database failover or similar
maintenance activity. This procedure reinstantiates the former primary database as
the new standby database.
When automatic database reinstantiation is enabled, a failed manual reinstantiation
attempt does not affect the reinstantiation timer. If a manual reinstantiation is
successful, the 5620 SAM does not attempt a subsequent reinstantiation.
Note — You must configure this parameter the same way on the
standby and primary main servers.
Note — When you stop the primary main server, a switchover to the
standby main server occurs.