Installation manual
20 031-171-C0-003 Rev. C
2.0 Site Preparation
2.1 General Information
Description
This document describes the installation procedures for the RMB-E-911-B and -C enclosures. The
process of installing the enclosure(s) are broken into four discrete procedures. If viewing this document
on-line, click a section below (blue text) to jump directly to it.
• Site Selection
• MiniBay Installation
• Battery Installation and Connection
• Utility Power Connection
2.2 Required tools and materials
For the following procedures, the installer(s) will need the following tools and materials on hand.
• Key to enclosure doors (p/n 964-022-10 — Pin Allen type, included)
• Battery Cabling Kit (included only for RMB-E-911-B)
• Crane to lift enclosure from shipping pallet and place on pedestal (not included)
• Digital RMS voltmeter (not included)
• Torque wrench with insulated handle and 7/16” socket (not included)
• 7/16” box-end wrench (not included)
• NO-OX or other suitable corrosion inhibiting agent (not included)
• Silicone sealant (GE RTV123, not included)
• “Pour in place” pad template (optional)
• Precast pad (optional)
• Concrete pad mounting hardware (optional)