7.3.2.9.2 Expected Result of Case #X
A successful PING command response should be received from each system.
7.3.3 Operation Tests
These test cases are designed to determine if OneRAN Pilot Station is ready for
production testing.
7.3.3.1 Test Case #1 – Voice Calls
7.3.3.1.1 Test Procedure
Test Call from MS #1 to MS #2.
Test Call from MS #1 to Landline Phone #1.
7.3.3.1.2 Excepted Result of Case #1
1. 2
nd
MS Rings and call is answered
2. Landline phone Rings and call is answered.
7.3.3.2 Test Case #2 – Data Calls
7.3.3.2.1 Test Procedure
1. A Test Data Call from MS #1 to MS #2.
2. A Test Data Call from MS #2 to MS #1.
7.3.3.2.2 Excepted Result of Case #2
1. A Data Session is established between MS #1 and MS #2.
2. A Data Session is established between MS #2 and MS #1.
7.3.4 Operator Specific Tests
These test cases are covered in a separate test plan document and are agreed to by the
operator and AirWalk Communications, Inc.
7.4 Site Clean up and Customer Signoff
7.4.1 Dispose of all packing material.
Make sure to dispose of all OneRAN Pilot Station packing material.
7.4.2 Clean-up site
Make sure not to leave anything but the installed OneRAN Pilot Station. (e.g., excess tie-
wraps, bolts, etc).