User's Manual

AirSynergy 2000 Installation Guide
Page 45 Commercial in Confidence UGD-D01001 Rev A
Advice: It is good practice to label both ends of the Network cable to identify
which AirSynergy unit it is connected to. This is especially important where
numerous AirSynergy units are installed on the same pole/tower.
Advice: It is good practice to leave a spare loop of network cable (approximately
0.5m). This will allow for easier wiring to the Network switch and will allow the
cable to be re-terminated if necessary in the future.
Figure 33 - power and network cable overview
7.3 Wiring Power Drop Cable to the PSU
The power drop cable supplied is a standard 30m (98.42 ft) length with the power connector end
for the AirSynergy unit pre-fitted. (Longer lengths are available).
Figure 34 - Waterproof connector exploded view
1. Choose the location PSU and the route of the power cable. Pass the cable through any
building walls or cable entry glands and bring the unterminated end to the location of
the PSU.
2. With the power drop cable from the AirSynergy cut to the required length prepare the
cable to fit the waterproof power connector.
3. Strip back and remove the outer sheath to expose the inner blue and black insulated
wires to a length of 3cm (1.18 in). Then strip back 6mm (0.24 in) of the inner core
insulation.
Figure 35 - power cable preparation