2. Hook the studs into the top slots of the mounting plate.
Figure 24 - unit engages into slots on the top of mounting plate
3. With the studs engaged in the top slots raise the unit slightly until the bottom studs also
drop into their respective slots.
Figure 25 - Gently lift the unit until the bottom studs fit into the bottom slots
Figure 26 - AirSynergy unit engaged into the bottom slots
4. Tighten the flange nuts (4 places) to the required degree of down-tilt.
5. Check and tighten all flange nuts.
5.5 LED Display
A single tri-color LED (Green/Red/Orange) appears at the bottom of the unit, providing unit status
indication.
When powering up refer to the following table for indication of current status:
Table 15 - LED Display
LED
Name
Color
Status
Description