8 Appendix A
Review Job Sheet
The Job Sheet should include the following information:
Pole for installation identified
Position on pole identified
Pole access restrictions (highway regulations, other services on pole, power pole)
Method of reaching pole positions (ladders, Elevated work platform)
AC main fuse block available for PSU (where needed)
Configuration programming details known
Point of connection for Ethernet (if applicable)
All equipment items available at the installation site
o Main AirSynergy unit
o Mounting bracket and pole clamps
o PSU
o Ethernet cable assembly
o GPS Antenna
o GPS antenna installation kit
o Front sector Antenna (if applicable)
o Front sector Antenna mounting bracket ad fixing kit (if applicable)
o External panel antenna (if applicable)
o RF feeder cable tails (if applicable)
Required tools
o Large flat screw driver for pole clamps
o Small flat blade screw driver (insulated shaft recommended)
o Medium Philips head screw driver
o 13mm wrench or small pipe wrench
o 10mm wrench for unit mounting flange nuts
o Knife
o pliers
o Small side cutters
o Tweezers (or fine blade long nose pliers)
o Wire strippers
o Ring terminal crimping tool
o Tilt-meter
Required ancillary equipment
o Laptop PC for initial configuration
o Ethernet cable for temporary connection of the lap top
Other install materials
o Self-amalgamating tape
o Black PVC tape
o Cable ties
Labels
Whether the system is required to be locked to a GPS timing reference..