4.3 Single Mode LC Cable Insertion
The fiber cable to be used is Single Mode fiber with LC connector. The SFP used inside the
product is Finisar FTLF1318P3BTL so make sure the other side can interoperate with this
SFP.
The following displays the proper steps for SFP cable preparation:
1. Have the pre-assembled LC connector Single Mode fiber cable ready.
Figure 13: Pre-assembled Single Mode LC Cable
2. Remove the caps from the LC connector.
3. Insert the LC connector of the Single Mode fiber cable into the connector. Verify when
engaged.
4.4 DC Cable Preparation
The following demonstrates the recommended assembly instructions, hardware and tool
requirements for the proper DC cable assembly used by Airspan products.
Power Cable:
Diameter - 8.4mm to 9.4mm
Wire Size - AWG16 to AWG14
!
Safety - Disconnection of power supply
When AirSpeed unit is connected directly to wiring a suitably rated and easily
accessible circuit breaker shall be incorporated externally to the equipment.
Power source disconnection is required before disconnecting the power
connector.
WARNING: This unit incorporates Double Pole/Neutral Fusing. Both the Line &
Neutral have fuses in them.
WARNING: The onsite source circuit breaker (6A) should be gang operated, two (2)
pole (single phase type).
The following displays the proper steps for DC cable preparation:
1. Strip back and remove the outer sheath to a length of 9.0mm± 2 (0.35 in) to expose the
inner insulated wires to a length of 13.5mm± 2 (0.53 in). Then strip back 7mm± 2 (0.27 in) of
the inner core insulation.