A I R S P E E D 2900 I N S T A L L A T I O N G U I D E 5G Outdoor gNB Installation Guide Document Part Number: DUG01085 Document Revision: A Published: November 2021
© Copyright by Airspan Networks Ltd., 2021. All rights reserved worldwide. Legal Notices The information contained within this document is proprietary, privileged and intended only for the recipient. As such, the information is subject to all relevant copyright, patent and other laws protecting intellectual property, as well as any specific agreements protecting Airspan Networks Ltd. rights in the aforesaid information.
AirSpeed 2900 gNB 5G OD Installation Guide TABLE OF CONTENTS Document Information ................................................................................................................... 4 Revision History ................................................................................................................................ 4 Warnings and Cautions ...................................................................................................................
AirSpeed 2900 gNB 5G OD Installation Guide 2.2.6 Environmental ............................................................................................................... 21 3 AirSpeed 2900 Installation ............................................................................................... 22 3.1 Connecting the GPS Antenna ........................................................................................... 22 3.1.1 Weather-proofing the GPS Antenna Connection ..........................
AirSpeed 2900 gNB 5G OD Installation Guide TABLES Table 1: AirSpeed 2900 gNB Maximum Output TX Total Power ................................................................ 12 Table 2: Voltage & Amperage Draws ........................................................................................................... 12 Table 3: Integrated Antenna Parameters .................................................................................................... 13 Table 4: Typographic Conventions ...............
AirSpeed 2900 gNB 5G OD Installation Guide Document Information This document details procedures for installing the Airspan’s AirSpeed 2900 gNB 5GB Outdoor unit. AirSpeed 2900 is a compact, easy to deploy gNB, for pole and wall installation. This document is intended for qualified personnel with a working knowledge of 5G. Revision History Revision Date Summary of Changes Created by Rev 0.1 - 0.
AirSpeed 2900 gNB 5G OD Installation Guide Warnings and Cautions Human Exposure to Radio Frequencies The AirSpeed 2900 gNB 5G OD unit should be operated from a minimum safe distance of 93 cm (3.05ft.) Radio Interference The AirSpeed 2900 generates, uses, and can radiate radio frequency energy and, if not installed and used in accordance with the instructions, may cause harmful interference to radio communications.
AirSpeed 2900 gNB 5G OD Installation Guide General • • • • • • • • Only qualified personnel should be allowed to install, replace, and service the equipment. The device cannot be sold retail, to the general public or by mail order. It must be sold to operators. Installation must be controlled. Installation must be performed by licensed professionals. Installation requires special training.
AirSpeed 2900 gNB 5G OD Installation Guide Safety 1. Read this guide and follow all operating and safety instructions. 2. Supply cord is not shipped with the unit and is to be provided by user. Installation is to be performed by a qualified electrician according to local codes. Installation to be done in accordance with the National Electrical Code (NEC), ANSI/NFPA 70, the Canadian Electrical Code (CEC), Part I, CAN/CSA C22.1, and when applicable, the National Electrical Safety Code, IEEE C2. 3.
AirSpeed 2900 gNB 5G OD Installation Guide Warning Symbols The following symbols may be encountered during installation or troubleshooting. These warning symbols mean danger. Bodily injury may result if you are not aware of the safety hazards involved in working with electrical equipment and radio transmitters. Familiarize yourself with standard safety practices before continuing.
AirSpeed 2900 gNB 5G OD Installation Guide - Poorly grounded tower/antenna sites that can conduct high lightning strike energy into equipment. - Lack of properly installed lightning protection equipment that can cause equipment failures from lightning induced currents. A lighting protection system provides a means by which the energy may enter earth without passing through and damaging parts of a structure.
AirSpeed 2900 gNB 5G OD Installation Guide This equipment is in compliance with the essential requirements and other relevant provisions of Directive 2014/53/EU. Español: Por medio de este Airspan, declara que la unidad cumple con los requisitos esenciales y cualquier otra disposición aplicable o exigible de la Directiva 2014/53 / UE. Greek: ΜΕ ΤΗΝ ΠΑΡΟΥΣΑ ΠΡΟΔΙΑΓΡΑΦΗ, η Airspan ΔΗΛΩΝΕΤΑΙ ότι η μονάδα συμμορφώνεται με τις ουσιώδεις απαιτήσεις και τις λοιπές σχετικές διατάξεις της οδηγίας 2014/53 / ΕE.
AirSpeed 2900 gNB 5G OD Installation Guide Slovak: Airspan týmto vyhlasuje, že tento prístroj spĺňa základné požiadavky a všetky príslušné ustanovenia Smernice 2014/53 / EÚ. Suomalainen: Airspan vakuuttaa täten, että laitteen tyyppi on direktiivin 2014/53 / EU olennaisten vaatimusten ja muiden asiaankuuluvien säännösten mukainen. Swedish: Därmed intygar Airspan att denna enhet överensstämmer med de väsentliga egenskapskraven och andra relevanta bestämmelser som anges i direktiv 2014/53 / EU.
AirSpeed 2900 gNB 5G OD Installation Guide GPS Compliance The GPS is in compliance with the essential requirements and other relevant provisions of Directive 2014/53/EU.
AirSpeed 2900 gNB 5G OD Installation Guide Antenna System The AirSpeed 2900 supports the following antenna options: • • • Integrated antenna – front mount integrated antenna, supports two carriers, 2x 2T2R. External antenna – 4 ports to two external antennas. Each antenna can serve a 2T2R sector in different directions. Hybrid – single sector via the integrated antenna and a second sector via the external antenna.
AirSpeed 2900 gNB 5G OD Installation Guide About this Document Purpose This guide provides the workflow and step-by-step procedures for installing the Airspan’s AirSpeed 2900 gNB 5G Outdoor. These procedures include: ➢ ➢ ➢ ➢ Verify prerequisites Install Tilt bracket & Pole/Wall bracket Install the AirSpeed 2900 Connect and manage cables Intended Audience This guide is intended for persons who are responsible for installing the AirSpeed 2900 equipment.
AirSpeed 2900 gNB 5G OD Installation Guide Related Reading The following documents contain related information: • • AirSpeed 2900 gNB 5G OD Product Specification Airspan 5G Commissioning Manual (pending) Customer Care Help Desk Airspan’s Customer Care Help Desk offers prompt and efficient customer support services. To avail Airspan’s Customer Care Help Desk support, you must be a registered user and must have a valid support contract. To register, click here and fill the Registration form.
AirSpeed 2900 gNB 5G OD Installation Guide 1 Getting Started 1.1 AirSpeed 2900 Installation Checklist Plan the installation of the AirSpeed 2900 by using the Installation Checklist, which you can find as a removable job aid in Appendix A for this guide. Figure 1: AirSpeed 2900 with GPS attached 16 © Copyright Airspan Networks Ltd., 2021 P/N DUG01085 Rev.
AirSpeed 2900 gNB 5G OD Installation Guide 2 Verifying Prerequisites Prior to installing the AirSpeed 2900 gNB 5G, verify the required safety, power, tools, parts and components. This chapter includes the hardware, software, and client requirements for installation. 2.1 Verifying Site Requirements Verify where the AirSpeed unit is to be installed, access and installation method. 2.2 Verify Installation Requirements 2.2.1 Verify the Tools Table 5.
AirSpeed 2900 gNB 5G OD Installation Guide 2.2.2 Verify the Parts and Kits Verify order and requirements to ensure the correct unit type is being installed. Table 6. Parts & Kits Installation Kit / Part AirSpeed 2900, 3.55-3.
AirSpeed 2900 gNB 5G OD Installation Guide 2.2.3 Power Supply AirSpeed 2900 supports direct connection to -48VDC power source: ▪ Operational Voltage Range: -40.5V to -57V DC 2.2.4 Connections The following diagrams display the connections on the top and bottom panels of the AirSpeed 2900. The unit requires a secure ground connection and a grounding screw fitted with a flat washer and lock washer is provided on the back and clearly marked with the universal ground symbol.
AirSpeed 2900 gNB 5G OD Installation Guide Figure 3: AirSpeed 2900 Bottom Ports 20 © Copyright Airspan Networks Ltd., 2021 P/N DUG01085 Rev.
AirSpeed 2900 gNB 5G OD Installation Guide 2.2.5 Physical Dimensions AirSpeed 2900 is an outdoor enclosure. The Airspeed 2900 should be only be installed in a restricted area. Table 7. AirSpeed 2900 Physical Dimensions Variant Dimensions (H x W x D) AS29-N48-DSC1 – Integrated antenna 496 x 279 x 131 mm / 19.53 x 10.98 x 5.16in. Weight Main Unit 9 Kg / 19.84 Lbs. Mounting Bracket (Bracket Base) 1 Kg. / 2.2 Lbs. 2.2.
AirSpeed 2900 gNB 5G OD Installation Guide 3 AirSpeed 2900 Installation AirSpeed 2900 can be installed outdoors on either a pole or a wall. The Mounting Kit - includes a Tilt bracket and pole/wall mounting bracket for fastening the unit to a pole or on a wall. Prior to installation the Tilt bracket must be assembled on the AirSpeed unit and then the mounting bracket must be affixed in place on either the pole or a wall. 3.
AirSpeed 2900 gNB 5G OD Installation Guide Figure 5: Tilt bracket Assembly 3.3 Pole Mounting Assembly Mount the AirSpeed 2900 unit in an orientation such that the RF connectors are facing up, and power/BH connectors are facing down. The following describes the pole mounting procedure: 1. Remove the upper two (2) screws from the Pole/Wall bracket and set them aside to be used later. Loosen the lower two (2) screws so they protrude from the Pole/Wall bracket. 2.
AirSpeed 2900 gNB 5G OD Installation Guide Figure 6: Position on Pole 6. Insert a clinch clamp on the two (2) upper threaded rods and put on washers and nuts and hand tighten. 7. Insert the bottom clinch clamp on the two (2) lower threaded rods and put on washers and nuts and hand tighten, as shown below: Figure 7: Mounting Bracket on Pole 8. Tighten all four (4) nuts. Fastening torque of 132 [Lib*in] = [151.8 kgf*cm]. 9.
AirSpeed 2900 gNB 5G OD Installation Guide Figure 8: Pole Mounting Assembly The following displays the AirSpeed 2900 mounted on a pole. Figure 9: Mounted on Pole 25 © Copyright Airspan Networks Ltd., 2021 P/N DUG01085 Rev.
AirSpeed 2900 gNB 5G OD Installation Guide 3.4 Wall Mount Assembly The following describes the wall mounting procedure: 1. Select the location on the wall to mount the AirSpeed 2900 mounting bracket. 2. Remove the upper two (2) screws from the Pole/Wall bracket and set them aside to be used later. Loosen the lower two (2) screws so they protrude from the Pole/Wall bracket. 3. Position the Pole/Wall bracket onto the wall at the required height and mark where to drill the holes. 4.
AirSpeed 2900 gNB 5G OD Installation Guide 3.5 Tilt Adjustment On the AirSpeed 2900 it is possible, after assembly to adjust the unit’s tilt, either up or down. This allows for maximum system optimization and reduce interference while increasing coverage. There are adjustment slots located on the sides of unit body where it is attached to the Mounting bracket. The AirSpeed 2900 unit body has a yield of a maximum tilt of +20° (up) and -30° (down).
AirSpeed 2900 gNB 5G OD Installation Guide 4 Connect and Manage Cables The following section explains the grounding procedure, cable preparation, external antenna assembly and general instructions on how to connect the DC power cable and the Fiber Ethernet (SFP) cable to the AirSpeed 2900 unit. Grounding cable, Fiber Ethernet cable, SFP connector adaptor and DC power cables are not supplied as part of the AirSpeed 2900 and can be ordered separately. 4.
AirSpeed 2900 gNB 5G OD Installation Guide 4.2 LED Display Two LEDs are displayed on the inside of the panel of the unit, providing unit status indication reporting system status: System / Access, Backhaul. These are software controlled to provide a visual indication to the Installer and is illuminated once power is applied to the unit. It can be turned off during normal operation.
AirSpeed 2900 gNB 5G OD Installation Guide 4.3 Single Mode LC Cable Insertion The fiber cable to be used is Single Mode fiber with LC connector. The SFP used inside the product is Finisar FTLF1318P3BTL so make sure the other side can interoperate with this SFP. The following displays the proper steps for SFP cable preparation: 1. Have the pre-assembled LC connector Single Mode fiber cable ready. Figure 13: Pre-assembled Single Mode LC Cable 2. Remove the caps from the LC connector. 3.
AirSpeed 2900 gNB 5G OD Installation Guide Figure 14: Stripping Dimensions (DC Cable) 2. Open the housing lock by sliding up then lift the clamp handle. Figure 15: Open Housing Lock 3. Separate the housing into its component sections. Figure 16: Separate into Sections 4. Insert the Gland nut through the other end of the cable. Figure 17: Insert Gland Nut 5. Loosen the strap clamp and feed the prepared end of the source power cable into the inner part of the DC connector housing.
AirSpeed 2900 gNB 5G OD Installation Guide 6. ! Secure the prepared ends of the cable into the inner part of the connector housing and tighten the 2 screws. Verify the wire polarity before securing, as shown in figure 19. Figure 19: Power Wire Connection Figure 20: Tightening of Set Screws 7. Tighten the strap clamp screw as shown below. Figure 21: Tighten the Strap Clamp 8. Insert into outer housing until “click” in place, align marks for proper alignment.
AirSpeed 2900 gNB 5G OD Installation Guide Figure 23: Place Split Rubber Gland 10. Place the tightening cone onto the split rubber gland. Figure 24: Place Tightening Cone on Split Gland 11. Tighten the gland nut with a 21mm wrench, to a torque of no more than 2-2.5 Nm (1.47 – 1.84 ft-lb) max. Figure 25: Tighten gland Nut 12. Insert the connector into the Power port on the bottom of the chassis. Verify that the connector’s latch faces the rear of the unit to enable potential unlocking. 13.
AirSpeed 2900 gNB 5G OD Installation Guide Appendix A. Installation Checklist During installation, review and perform all the steps on this checklist (in the given order). This checklist is meant for the person who performs the AirSpeed 2900 installation. To make sure you complete all the tasks, detach or print this checklist and use it as a job aid. After performing, check off each task. Procedure Verify the prerequisites Action Check If Performed Verify the site requirements.
AirSpeed 2900 gNB 5G OD Installation Guide Appendix B. Abbreviations Table 9: ABBREVIATIONS & DEFINITIONS Term Expansion dB Decibel. A logarithmic unit used to describe a ratio (such as power ratio in radio telecommunications) dBm An abbreviation for the power ratio in decibels (dB) of the measured power referenced to one milliwatt (mW).