Installation Guide
AirSpeed 1050 Installation Guide
DUG01545 Airspan Commercial and Internal Use 30
14. After tightening the gland nut, close the lever.
Figure 25: Close the Lever
15. Secure the lock by sliding the secondary lock/button; assembly is now ready
Figure 26: Secure Lock
Note: When securing the cable verify there is no tension on the connector so that it is easy to
disconnect and re-connect for future maintenance actions.
Note: After locking the secondary lock/button and lever, it is required to fasten down the lever
mechanism with the supplied metal tie (to prevent easy opening) and verify that it is secure, as
shown in Figure 68: AC Housing Lock Secured.
5.2.2 DC Cable Preparation
The following displays the proper steps for DC cable preparation:
1. Strip back and remove the outer sheath to a length of 9.0mm± 2 (0.35 in) to expose the inner
insulated wires to a length of 13.5mm± 2 (0.53 in). Then strip back 7mm± 2 (0.27 in) of the
inner core insulation.
Figure 27: Stripping Dimensions (DC Cable)