User Manual
AS4000 Subscriber Terminal
Installation and Commissioning GSI 006
605-0000-436
Issue 1.5 Date: 18th October 1999
Page 4 of 4
4. Installation Check List.
Check site meets site selection criteria q
Position and fix CRU mounting bracket q
Install CRU q
Fix PSU to wall (type 2 & 4 only) q
Install power chord q
Earth PSU (if applicable) q
Fix junction box to wall (type 1 PSU only) q
Terminate the drop cable on PSU / Junction Box q
Stick on PSU logo label (type 4 PSU only) q
Fix cable strain relief (pole mount CRUs only) q
Fix house cable support bracket (pole mount CRUs only) q
Run drop cable q
Plug connector into CRU (ST-V2 and ST-I1) q
Terminate drop cable on CRU (D-128) q
Terminate the drop cable on PSU / Junction Box q
Run and terminate cable for NTUs q
Install interface adapter if required (D128 only) q
Connect batteries (Type 2 & 4 PSU only) q
Programme CRU q
Pan CRU q
Measure and record PC and AGC voltage on test form q
Functional tests record result on test form q
Clear and tidy site q