User's Manual
Table Of Contents
- Installation
- Overview AS4000
- Overview AS4020
- Preparation
- Rack Installation
- AS4000 AC Rack Cabling and Wiring
- AS4000 CT Shelf Cabling and Wiring
- _
- Expansion Rack Cabling
- Setup and Test
- System Testing
- AS4000 AC Setup and Test
- Access Concentrator: Turn-Up and DC measurements
- Setting Up the Access Concentrator
- _
- Setting the TEI and Baud Rate for Netspan Connection
- Creating AC Shelf/Rack on Sitespan
- Setting up AC Rack and Shelf configuration
- Configure AC Cards
- Configure AC Shelf properties
- Check Boot Sequence
- Alarm and Status Indications (Test 3)
- Self Test (Test 4)
- Test CTU cabling to the DDF E1 Cards
- Test CTU cabling to the Distribution Frame (DDF) GR303 Cards.
- Test XTU cabling to the DDF
- Connecting the AC to the Network
- Connect E1s/T1s to the Switch or Cross-Connect at the DDF
- Access Concentrator Rack Commissioning Test Results
- AS4000 CT Setup and Test
- AS4020 CT Setup and Test
- _
- General
- Repair and Return Procedure
- Repair Charges
- Return & Repair Tag
- Packing and Shipment
- Glossary
- Index
Printed Documentation
156
Central Terminal Rack Commissioning Test Results
Please photocopy test results sheet for use with each system
CUSTOMER:
SITE LOCATION:
RACK ID:
ENGINEER:
DATE:
Test Equipment Calibration
1.
Item
Description Model Serial No Calibration
Date
1 Digital Multimeter
2 RF Power Meter
3 Power Sensor
6 Test ST/DACU
7 60dB Variable
Attenuator
8 3dB Attenuator; 2W
9 30dB Attenuator; 1W
10 30dB Attenuator; 1W
11 30dB Attenuator; 2W
12 30dB Attenuators; 2W
DACU Calibration
Item
Description Output/loss Serial No Calibration
Date
1 DACU
2 RF Coupler Loss
3 RF Cable loss from
DACU to coupler