CT TX AND RX POWER SET-UP (2.0-2.3GHZ BAND) USING
TEST CRU
Note: This method of setting up the CT should be used if a Level Control Unit is not
available.
1. Tools and equipment needed.
Item Description Recommended Model Quantity
1 Digital Multimeter Fluke 77 1
2 Test CRU ACC(“Battleship CRU”)
Part No.: 503-0300-001
1
3 30dB Attenuators; 1W Suhner 6830-19-A 4
6 11dB Variable Attenuator HP8499B 1
7 2 Way Power Divider Narda 4313-2 3
8 50 ohm Termination 1W Suhner 65 SMA-50-0-1 1
9 50 ohm Termination 15W Suhner 6515.17.A 1
10 Adaptor; N-SMA Suhner 33N-SMA-50-1 2
11 Adaptor; N-SMA Suhner 31N-SMA-50-1 1
12 Adaptor; Female-Female Suhner 32 SMA-50-0-1 1
13 Co-ax Cables Suhner Sucoflex 104; 0.5m 5
Suhner Sucoflex 104; 4.0m 2
14 RF Power Meter Marconi 6970 1
15 Power Sensor Marconi 6932 1
STEP PROCEDURE
Observe full ESD precautions.
2. Note:
The system may be commissioned using either a Voice or a Data CRU as a test CRU. IF
using a Data CRU, it should be programmed using STMON (see 605-0000-436 for details)
and not a test telephone in step 6(e). If a Data CRU is being used for commissioning then
steps 6(f) and 6(h) are not necessary.
3. Preparation
a) System Soak The system must be switched on for at least 2 hours to ensure that it
is fully warmed up before proceeding any further. To minimise the down time the
test equipment can be prepared during this time ready for testing.