User Manual
AS4000 Central Terminal
Installation and Commissioning
DLP 006
605-0000-452
Issue 1.3dr Date 7/02/00
Page 1 of 4 © Copyright Airspan Communications Corporation 2000
COMMISSIONING TESTS
1. General
The following procedures need to be carried out in order to verify the functionality and
operation of all cards fitted into the Central Terminal Racks prior to placing the
AS4000 system into service.
If during testing, a fault occurs preventing the continuation of the test, the faulty
module or card should be replaced and the test repeated for the card and all tests that
are affected by the performance of that card.
All results must be entered on the Commissioning Test Result Sheet (DLP-013). Test
forms should be photocopied as needed, ensure that sufficient copies of the Modem
Functionality Tests sheet are available prior to the commencement of commissioning
tests.
2. Commissioning rack
The chart below shows the commissioning and testing process. The reference in
brackets is the corresponding paragraph in the text. Tests are shown with a rounded
corner box and procedures are shown in a square box. In addition each test has a
number indicating the order of testing and reference for the test record sheets.