2.2. Site Earth
Confirm the position of the grounding point using the site survey.
2.3. Flooring
Ensure that flooring is substantial enough to support the rack and can provide a secure
fixing.
2.4. Cable Trays
Verify that cable trays are installed to provide routing to the proper destinations and are
of adequate strength
2.5. Delivery Inspection
Upon taking delivery of the equipment consignment, check that the consignment agrees
in all particulars with the consignment delivery documentation (number of boxes,
descriptions, contents of boxes, etc.). Any discrepancy or damage must be reported
immediately to ACC for further instructions. In case of severe damage, do not accept the
consignment from the carrier. See Material Return and Repair document 605-0000-427.
for further details. The equipment is normally shipped as shown in. Figure 1
Rack (wooden crate)
Antenna Assembly
(one cardboard box)
CT plug in cards
(each in their own
individual packaging
inside a cardboard
box on a pallet)
Figure 1. Packaging for CT Site
If subsequent to the initial shipment incremental upgrades are made to the system the
equipment will be delivered in packaging of size and type suitable for that shipment.