User Manual
AS4000 Central Terminal
Installation and Commissioning
DLP 001
605-0000-452
Issue 1.3dr Date 7/02/00
Page 2 of 4
1.2. Required Equipment
Item Description Recommended Model Quantity
1 Digital Multimeter Fluke 77 or similar 1
2 50 ohm Termination 15W Suhner 6515.17.A 2
3 Frequency Generator up
to 2.1GHz
Signal Generator MI2024 1
4 Test Lead for TU Card ACC proprietary item 1
5 Coupler Test Lead Lead with SMA connector 1
6 RF Power Meter Marconi 6970 1
7 Power Sensor Marconi 6932 1
Table 1-1. Required Test Equipment.
2. Site Readiness
Verify that the site is ready for the installation of the CT Rack.
This preparation will have been covered by a ACC Site Survey or a survey form
completed by the customer. The survey will include a site plan of the facility Identifying
the floor layout, power outlets, distribution boxes, and cabling runways. A sketch
showing the rack support arrangements showing the exact positions of the mounting
points on the rack with dimensions, and typical overhead ironwork provision should be
included.
Inspect the site, and particularly the equipment room, before unloading or unpacking the
equipment to ensure the following:
• Adequate grounding is provided.
• Access to the equipment room will be adequate for normal handling and movement.
• Adequate lighting is available for carrying out the installation.
Any non compliance with acceptable standards should be bought to the customers
attention and resolved before proceeding with the installation
2.1. Power Availability
From the site survey, confirm the location of the two fuse positions for the negative
battery supply and the return point. The fuse position for the alarm unit 55B power
supply should also be located.