Installation Guide

AirSynergy Equipment Installation Guide
Page 33 Commercial in Confidence SYN-UG-007 Rev A0.41
6 Connect to Power System
Caution: Hazardous voltage! Before working, ensure that the power is removed
from the power connection cables. When the system is powered on, do not
touch the power terminals.
Tools Required: The tools required for the connection of the PSU and PoE
injector are: knife, small flat blade screw driver, medium cross-head screw driver,
pliers, small side cutters, tweezers (or fine blade long nose pliers) and punch
down tool (Krone or similar)
Figure 37 – Tools required to connect the PoE injector and PSU
6.1 Run cables from the PoE injector to the AirSynergy
6.1.1 The drop cable installation. If the drop cable is to be passed through glands and/or down the
centre of a lamp post or other structure, the drop cable can be cut leaving sufficient length for ease of
termination. (The cable length from the AirSynergy should be 20m max.) With the PoE injector
placed at the selected installation location, trim the cable length so that it will fit neatly to the box while
allowing sufficient length to strip and prepare the cable ends.
Note: It is good practice to label both ends of the drop cable to identify which
AirSynergy unit it is connected to. This is especially important where multiple
AirSynergy units are installed on the same pole/tower.