Specifications

To run the self-tests
Self-tests identify the correct operation of major functional areas of the instrument. You can
run all self-tests without accessing the interior of the instrument. If a self-test fails, the
troubleshooting flowcharts instruct you to change a part of the instrument.
These procedures assume the files on the PV disk have been copied to the /SYSTEM
subdirectory on the hard disk drive. If they have not already been copied, insert the PV disk
in the flexible disk drive before starting this procedure.
1
If you just did the power-up self-tests, go to step 2.
If you did not just do the power-up self-tests, disconnect all inputs, then turn on the
power switch. Wait until the power-up tests are complete.
2 Press the System key, then select the field next to System. Then, select Test in the
pop-up menu.
3 Select the box labeled Load Test System, then select Continue.
4 Press the System key, then select the field next to Sys PV. Select System Test to
access the system tests.
Troubleshooting
To run the self-tests
5–18