Technical data
Table Of Contents
- Contents
- Introduction
- System Description
- Installation
- Overview
- Step 1: Selecting a Location
- Step 2: Unpack and Inspect the Instrument
- Step 3: Set Up the Vacuum Pump
- Step 4: Connect the Power Cord
- Step 5: Install the Dry Compressed Air or O2 Supply
- Step 6: Install the Signal Output Cables
- Step 7: Install the Dual Plasma Burner
- Step 8: Install the Dual Plasma Controller
- Step 9: Install Column Connections
- Step 10: Install the Transfer Line
- Front Panel Controls and Initial Startup
- Operation
- Maintenance
- Pump Maintenance
- Cleaning the Detector
- Changing the Oil Mist Filter (RV5)
- Reaction Cell Cleaning
- Flow Sensor Calibration
- Detector Sensitivity
- Assembling the Dual Plasma Burner for Component Replacement with the SCD
- Assembling the Dual Plasma Burner for Component Replacement with the NCD
- Tube Replacement for the SCD
- Tube Replacement for the NCD
- Troubleshooting
- Index
94 Operation and Maintenance Manual
15
Carefully bend the H
2
line into position so that the 1/16" Valco nut and
ferrule can be screwed into the side port of the splitter fitting. Tighten the
connection of the H
2
line to the splitter fitting using a 3/8" wrench on the
vertical flat of the splitter fitting and 1/4" wrench on the Valco nut.
16 Make sure that no other connections have loosened or moved out of
alignment, if so, reposition or retighten the fittings as needed.
17 The assembled Burner is now ready for re-installation on the GC.