The performance verification tests have two parts: a closed channel
resistance test of all relay contacts (Test 2-1) and a DC isolation test (Test
2-2). These tests are sufficient to determine that the module is operating
within specifications. These tests are suitable for incoming inspection,
troubleshooting, and preventive maintenance.
Wiring the
Test Fixture
A test fixture is required for the performance verification tests. Figure 2-1
shows typical connections using an Agilent E1465A terminal module for the
test fixture. Figure 2-2 shows typical connections using an Agilent E1466A
terminal module for the test fixture. Figure 2-3 shows typical connections
using an Agilent E1467A terminal module for the test fixture.
Any one of these terminal modules may be used to test the component
assembly. You may want to order an extra terminal module to use as a test
fixture, so you don’t have to re-wire each time the tests are performed.
The terminal module part numbers are:
Module Terminal Module
(with release levers)
Terminal Module
(without release levers)
E1465A E1465-80010 E1465-80001
E1466A E1466-80010 E1466-80001
E1467A E1467-80010 E1467-80001
Figure 2-1. Agilent E1465A Test Fixture
Agilent E1465A/66A/67A Service Manual Verification Tests 21