Technical data

154 Agilent U7232A DisplayPort Electrical Performance Compliance Test Application
18 Sink Eye Diagram Tests
Probing for Sink Eye Diagram Tests
When performing the sink eye diagram test, the DisplayPort Electrical
Performance Compliance Test Application will prompt you to make the
proper connections. Your DisplayPort test environment setup on the Set
Up tab must match the physical connection.
Figure 48 and Figure 49 show a physical connection for making
differential and single- ended connections.
.
Infiniium Oscilloscope
1168A or 1169A Probe
Amplifier
N5380A SMA probe head.
Connect the plus side of
the probe to the plus side
of the SMA probe head
and the negative side of
the probe to the negative
side of the SMA probe head.
Lane on the test fixture
SMA to SMP cables
DUT
Figure 48 Probing for Differential Tests - Sink Eye Diagram Tests (Single Connection with
DisplayPort Test Fixture)