Technical data

76 U7232A DisplayPort Compliance Testing Notes
8 Source Pre-emphasis Level Verification Testing
channels of the oscilloscope. If you are using four connections, connect
the four probes to any four channels of the oscilloscope.
4 Connect the SMA to SMP cable to the SMA probe head of one of the
probes and to the data lane connector on the W2641A fixture that you
want to test.
5 Connect the other SMA to SMP cable to the other SMA probe head and
to the data lane on the W2641A test fixture that you want to test.
6 In the DisplayPort Compliance Test Application, click the Set Up tab.
7 Set the DUT Definition Driven Setting, the Test Type, the Fixture Type,
Lane- Channel Selection, Connection Settings, and the Connection Type
according to the type of testing being done.
.
8 Follow the DisplayPort Electrical Performance Compliance Test
Application’s task flow to set up configuration options (see
Table 9),
make oscilloscope connections, run the tests, and view the test results.
Figure 28 Selecting Pre-emphasis Tests