Technical data

2- 2 Agilent 41000 Administration Guide, Edition 3
Installation and Operation
This chapter describes how to install the Agilent 41000 and how to operate the Agilent
41000 system cabinet.
“Installation”
“Turning the PDU On and Off”
“Recovering from Power Line Problems”
“Maintenance”
NOTE About System Components
For the operation of the instruments (system components of the Agilent 41000), see
manuals of each instrument.
NOTE Site Preparation
You have to perform the site preparation before you receive the Agilent 41000. The site
preparation information is described in Agilent
41000 Preinstallation Guide that must be
delivered to you as soon as the order is accepted.
CAUTION Before Opening Packing Materials
The Agilent 41000 Model 200/300/400 contains the Agilent B2200 switching matrix that
uses the condensation sensitive electronic parts. The condensation will have a negative
impact on the Agilent B2200 to operate normally.
Do not open the packing materials, and leave the Agilent 41000 to acclimate it to the
installation environment (temperature and humidity). If it is opened without enough
acclimation, the Agilent B2200 may damage.
NOTE Unpacking
After enough time to acclimate the Agilent 41000 to your installation environment, open
the packing materials as shown below.
1. Unpack the system cabinet and accessories.
2. Move them to the installation location.
For details, see Agilent 41000 Preinstallation Guide.
NOTE Agilent 41000 Measurement Record of Integrity Verification
Keep this report that shows the measurement performance data, not specifications, when
the Agilent 41000 is shipped from the factory. The data is not guaranteed, but can be used
as a reference data when you verify the Agilent 41000 measurement performance by using
the Agilent iPACE Verification Tool.