Installation guide

5
Reconfiguring the
Application Server and
Curator
After the Server components are upgraded, you must configure the Application Server to work with
the production server instead of the training server and possibly convert the training server into a
Curator.
Reconfiguring the Application Server
(Topic number: 6809)
1.
During the preparing to upgrade period, the station intended to serve as the new Application Server
for the site is connected to a temporary AS300 single-host station. (This configuration option is
described in the Installing a training server cluster section of the AS300 Preparing to Upgrade
GuideIMPAX 4.5, 5.2, 5.3, or WEB1000 to IMPAX 6.5.3; also see the Training server configurations
diagram.)
AS300 Upgrade Guide—IMPAX 5.2 or 5.3 to IMPAX 6.5.3 39
Agfa Company Confidential—Subject to Non-Disclosure Obligation