Owner manual

Benchmark 1500DF - 2000DF Boilers
CHAPTER 2 INSTALLATION
Page 18 of 196 AERCO International, Inc. 100 Oritani Dr. Blauvelt, NY 10913 OMM-0098_0A
04/01/2014 Ph.: 800-526-0288 GF-144
Figure 2-2: Boiler Lifting Provisions
In multiple unit installations, it is important to plan the position of each unit in advance. Sufficient
space for piping connections and future service/maintenance requirements must also be taken
into consideration. All piping must include ample provisions for expansion.
If installing a Combination Control Panel (CCP) system, it is important to identify the
Combination Mode Boilers in advance and place them in the proper physical location. Refer to
Chapter 5 for information on Combination Mode Boilers.
LIFTING LUGS
(3 POSITIONS)
2” NATURAL
GAS INLET
1” PROPANE
INLET