7. Double check work – Label conductors & SPDs - Energize Tower Light Controller
Double check work – conrm that correct SPDs are installed to correct circuits.
If in doubt – please contact APT Tech Support at (800) 237-4567.
Double check torque to 7 lb-in.
Double check that ground terminals are tight to DIN Rail
Upon verication that SPDs are installed correctly,
Label each wire bundle for ease of future service, and label each SPD
Energize circuits
Individual SPD LED indicators should illuminate correctly.
Install TWL cover.
Advanced Topics:
Two TWLs side by side, or one above or below the other. (Figure 8):
Mount appropriately. Ensure solid ground connection between two TWLs via 4” copper ground strap.
Remote SPD Diagnostic Indication:
Most APT SPDs are available with optional Dry Contacts for remote monitoring purposes. These indicate A-OK/Good or Failed
status. See individual SPD datasheets for more information. SPDs must be ordered with this option and cannot be eld retro-t.
When equipped, the SPD includes additional Form C Dry Contact wires. These wires may be connected to additional feed-
through terminal blocks for remote connection elsewhere.
(800) 237-4567
·
(727) 535-6339
·
Fax (727) 539-8955
UL is a registered trademark of Underwriters Laboratories, NEC and National Electrical Code are registered trademarks of National Fire Protection Association,
C62.41.1-2002, C62.41.2-2002, C62.45-2002, C62.72-2007 are registered trademarks of IEEE.
Advanced Protection Technologies
www.apttvss.com
·
info@apttvss.com
·
www.aptsurge.com
14550 58th Street North
·
Clearwater, Florida 33760
5.29.12 #8615
European Authorized Representative
Obelis s.a.
Boulevard Général Wahis 53
1030 Brussels, BELGIUM
Tel: +(32) 2. 732.59.54
Fax: +(32) 2. 732.60.03
E-Mail: mail@obelis.net
Questions?? Need Assistance?? Contact APT at 800.237.4567 or Info@aptsurge.com.
Figure 8
Page 9
4" copper ground strap
interconnects two TWLs
To Ground
Bonding Multiple TWLs Together