LEADS SHORT & STRAIGHT
X
NOT
GOOD
GOOD
Cut off
Excess Length
Do Not Loop
or Coil
Short
& Straight
Figure 2
A
BC
GN
BREAKER
(Type 1 or individual equipment installations may vary)
Use closest
breaker to SPD
Locate SPD close
to intended breaker
Keep Leads Short
as Possible
Avoid Sharp Bends
Rotate SPD
ee
such
that LED indicator
is most visible
Outdoor installation requires appropriate weather
sealing at nipple (gasket, sealing conduit, etc.)
To Protected Loads
Figure 1
Sealing gasket:
two choices
1.) At 3/4" nom.
thread: ID is 1.05"
2.) At 0.14" high 'base
step': ID is 1.25"
Figure 3
INSTALLATION
Pre-Plan your installation. You need to accomplish the following:
Meet all National and Local codes (NEC
®
Article 285 and UL 1449 address SPDs).
Conrm System voltage to SPD voltage (120V SPD will fail instantly on 240V, 277V, etc.).
Mount SPD as close to panel or equipment as possible to keep leads short.
(long leads hurt performance substantially).
Ensure leads are as short and straight as possible, including neutral and ground. If using a
breaker, use a breaker position that is close to the SPD and the panel’s neutral & ground.
If using a breaker, recommended breaker size is 30A due to 10 AWG conductor.
Make sure system is grounded per NEC
®
and clear of faults before energizing SPD.
(inadvertent system problem may fail SPD).
Never Hi-Pot test Any SPD. (will prematurely fail SPD).
1. Use voltmeter to check voltages and ensure correct SPD. See Data Sheet for specs and wire-outs.
2. Determine Mounting method (See Figure 5) – weather resistant equipment may be required.
3. If SPD has optional Dry Contact, pre-plan its installation.
4. Remove power from panel/source. Conrm panel/source is deenergized.
5. Identify breaker location and SPD location. Position SPD such that LED is best visible.
6. Mount SPD – weather resistant applications require additional sealing, o-rings, etc. (not included)
- Remove an appropriately sized knockout from panel.
- Connect conductors as appropriate – short and straight as possible (Hi-Legs are Phase B).
7. Label or mark conductors as appropriate (neutral: white, ground: green, energized: black, hi-leg: orange).
8. Make sure system is bonded per NEC
®
and is clear of hazards or faults before energizing.
(N-G bonding not per NEC
®
will fail SPDs: #1 cause of SPD failures)
9. Energize and conrm proper operation of green LED indicator and/or options.
(Afx supplemental label accessory if appropriate. See Figure 5.)
V
WARNING
Conrm XO N-G Bonding at Upstream Transformer
Do Not Hi-Pot Test
Resulting Damage is not Covered Under Warranty
VERIFY THAT ALL POWER CIRCUITS ARE
DEENERGIZED BEFORE MAKING CONNECTIONS
All electrical connections should be performed by a qualied
(licensed) electrician or technician. All wiring must comply with
the National Electrical Code (NEC
®
) and applicable local codes.
TYPICAL PANEL
INSTALLATION
V
WARNING