6. INSTALLATION
6.1 Pre-Installation Inspection
Please follow these procedures before installing ADX equipment:
o Verify the number of packages received against the packing list.
o Check all packages for external damage; report any external damage to the shipping carrier. If
there is damage, a shipping agent should be present before you unpack and inspect the contents
because damage caused during transit is the responsibility of the shipping agent.
o Open and check each package against the packing list. If any items are missing, contact ADRF
customer service.
o If damage is discovered at the time of installation, contact the shipping agent.
o Verify the AC voltage with DVM (Volt meter), then select the either 110V or 220V AC using the
selection switch located at the rear of HE and RU PSU. The ADX ships with the AC selection
switch set to the 110V position. Incorrect AC selection can damage the ADX equipment.
6.2 ADX DAS Installation Procedure
6.2.1 HE Installation Procedure
CAUTION: ADX DAS HE should be installed inside building only.
6.2.1.1 Installing a ADX DAS HE in a rack
The ADX HE chassis mounts in a standard 19(483mm) equipment rack. Allow clearance of 3” (76mm) at the
front and rear, and 2” (51mm) on both sides for air circulation. No top or bottom clearance is required.
x Consideration:
- Eight mounting holes are located on 4 corners of ADX HE to attach it to the 19” rack. The ADX HE must be
securely attached to a rack that can support the weight of the ADX.
x Mount procedure
- The following steps should be followed while mounting the ADX HE
! Detach the wall mount bracket assembled located at the base of the ADX-HE chassis
! Verify that the HE and Mounting holes are in good condition
! Set the ADX DAS HE against the 19”rack and secure the unit with screws
! Verify that ADX HE is securely attached
! Connect the GND cable
! Connect the RF cable
! Connect the Power
! Connect the Optic cable