7. COMMISSIONING
The commissioning process is composed of the following:
- Pre-Commissioning Check (refer to section 7.1)
- Optic Commissioning (Optic loss compensation) (refer to section 7.2.1)
- HE commissioning (refer to section 7.2.2)
- RU commissioning (refer to section 0)
- Commissioning verification (refer to section 0)
7.1 Pre-Commissioning Check
7.1.1 Verify cable connections
x Before powering up units, check all RF cables, fiber cables, and power cables connections.
x All power LEDs should be lit 1 minute after the components have been turned on.
x Check whether LD & PD LEDs of HE ODU modules are solid GREEN. (PD LED will be lit green when connected to
a Master RU).
- If the PD LED for the link with a connection with to a HRU is OFF, then check the optic cable
connection.
- If the optic cable is good and the PD LED is not lit green, the try another optic port on the ADX-
RACK-ODU to see if the other port lights up green.
7.1.2 Connect to the Web-GUI
x Confirm that the NMS Host/Remote switch is set to the Host position
x Confirm that the HE View/RU View switch is set to the HE View position
x Connect the RJ-45 crossover cable from the Ethernet port of NMS to the Ethernet port of laptop
x Launch a standard Internet browser like IE or Google Chrome and type the System Controller’s IP address
(192.168.63.1) into the addess bar
x On the login screen use the following default login/password to gain access:
- Username: adrf
- Password: adrf
Figure 7-1 Login window