User's Manual
Table Of Contents
- SECTION 6 Installing Unison Accel
- 6.1 Installation Requirements
- 6.2 Safety Precautions
- 6.3 Preparing for System Installation
- 6.4 Unison Accel Installation Procedures
- 6.5 Interfacing an Accel Hub to a Base Station or a Roof-top Antenna
- 6.6 Connecting Contact Alarms to an Accel System
- 6.7 Alarm Monitoring Connectivity Options
- SECTION 7 Replacing Unison Accel Components in an Operational System
- SECTION 8 Maintenance, Troubleshooting, and Technical Assistance
- APPENDIX A Cables and Connectors
- APPENDIX B InterReach Unison Accel Property Sheet
- APPENDIX C Compliance
- APPENDIX D Release Notes
PN 9000-10 Help Hot Line (U.S. only): 1-800-530-9960 6-13
620021-0 Rev. A
Connecting the ScTP Cables
Consideration:
• Verify that the cable has been tested and the test results are recorded.
To test and connect the ScTP cable:
1. Perform cable testing.
Test results are required for the final As-Built Document.
Cable length:
– Minimum: 10 m (33 ft)
– Recommended Maximum: 100 m (328 ft)
– Absolute Maximum: 150 m (492 ft)
2. Label both ends of each cable with which RJ-45 port you’re using.
3. Connect the ScTP cables to any available RJ-45 port on the Accel Hub.
The
LINK and RAU LEDs should be off because the RAU is not connected.
4. Record which cable you are connecting to which port.
This information is required for the As-Built Document.
5. Tie-off cables or use the optional cable manager to avoid damaging the connec-
tors because of cable strain.