User's Manual

System Management
FlexWave Prism Element Management System 7.1 User Manual Page 135
ADCP-77-177 Issue 1July 2011 © 2011 ADC Telecommunications, Inc.
SCHEDULE SYSTEM TEST
You can schedule a System Test to run on a specific date and time, as described in:
“Schedule System Tests by Date and Time” on page 135
“Disable a Scheduled System Test” on page 137
Schedule System Tests by Date and Time
CAUTION! Running System Test (System Configuration > Perform System Test) with un-terminated Host
DARTs may cause a false RLM Upconvert Fault. Ensure that all Host DARTs are terminated before
running System Test.
CAUTION! System Test interrupts RF transmission; System Test should therefore only be run during a normal
maintenance window.
CAUTION! Do not make any software or hardware configuration changes during System Test, as changes
made during the test will make the test results unreliable.
Do the following to schedule a single or recurring System Test:
1 In the System Menu bar, click System Configuration > Schedule System Test.
2 Select Enable to enable the scheduled System Test (see also “Disable a
Scheduled System Test” on page 137).
3 In the Bands list, select the band(s) that you want to test.
4 In the DART list, select the DART(s) that you want to test.