23) Verify telnet communications with the IWP card by terminating the serial connection by entering
~. (tilde .), which returns the prompt to build@craftpc:~>.
After the serial connection is terminated, enter telnet bts to display the bts:A-> prompt. This
shows that you are able to set up a telnet session with the TurboMAX.
Terminate the telnet session by entering logout. This causes the TurboMAX to display Connection
closed by foreign host and the prompt changes back to build@craftpc:~>.
24) Reestablish a serial connection with the TurboMAX by entering cu l ttyS0 s 9600. The
TurboMAX responds with Connected. Press the [ENTER] key to display the bts:A-> prompt.
25) At the bts:A-> prompt, enter runtrxpost to test the TRX card(s). The resulting output contains the
output for the various TRX tests, including one line for each TRX that reads: TRX CARD IN SLOT
<2, 4, or 6>: COMPLETED TRX POST OFFLINE TEST: <PASSED/FAILED>.
26) Review the E1/T1 and BTS POST test results by entering postReportE1Trx. The TurboMAX
displays a summary of the E1/T1 and TRX test results, which should all appear as PASSED except
those which appear as NOT-RUN.
27) Reboot the TurboMAX after running the POST tests by entering reboot at the bts:A-> prompt.
28) Have the E1 or T1 link provider certify that the links pass a BER (Bit Error Rate or Bit Error Ratio)
test at 10
-8
or better over 20 minutes.
29) Reconnect all E1 or T1 cables disconnected to run the POST tests.
3.6 Performing Racal Tests
30) Perform the Racal Test procedures for the TurboMAX as described in the interWAVE Field
Maintenance Guide for the 16W TurboWAVE. The only difference is that the output power of the
TurboMAX is slightly higher.
3.7 Off-Line Commissioning of a TurboMAX Daisy Chain
This is an optional section, and is only required if multiple TurboMAXs are to be daisy-chained off of a
BSC, BS Plus, or NIB. If this configuration is used, each TurboMAX must be installed separately, and must
have off-line commissioning procedures independently performed. Once each TurboMAX is installed and
commissioned, the TurboMAXs can be daisy chained together.
31) Before connecting any TurboMAXs, ensure that they are all installed and off-line commissioned.
32) Ensure that all the TurboMAXs have been tested using the Racal Test Set.
33) Ensure that a different Abis link has been set for each TurboMAX using the Abis Manager time slot
has been set for each TurboMAX as follows:
After each TurboMAX has been Racal tested, enter getFlashE1Chan at the Craft PC bts:A->
prompt. The TurboMAX displays the timeslot reserved for the LAPD signaling timeslot (default =
16).
To change this value, enter setFlashE1Chan <timeslot> at the Craft PC bts:A-> prompt,
where<number> is any unassigned E1 or T1 timeslot between 1 and 31, or between 1 and 24,
respectively.
Note that interWAVE recommends the following Abis timeslot assignments: First TurboMAX in the
daisy chain, Abis timeslot = 16. Second TurboMAX in the daisy chain, Abis timeslot = 17. Third